Project Milestones

Combined Cannabis Experience

125

Years

Project Milestones

PowerPlant Park enters a vast and lucrative California market, facing historically low levels of premium /ultra-premium flower. Inventory of turnkey space is extremely hard to find in California, especially in the San Francisco Bay Area. The Park is now two years into Phase I construction, the design/drawings completed by a team of over 40 renowned local area engineers, architects, consultants, and designers.

View Milestones

Milestones Completed

  1. PowerPlant Park was unanimously granted its CUP and land use entitlements from Richmond’s Planning Commission on April 20th, 2019. The approval process spanned over 36 months working closely with City and State officials

  2. PowerPlant Park began construction in November 2020, interrupted due to Richmond’s Covid’s moratorium on new construction. Construction resumed late April of 2021, currently the first 5 Greenhouse in Phase I Part A are 80% completed, onsite infrastructure/utilities are 95% complete

  3. PowerPlant Park filed for its CUP approved State Licenses in November of 2022, are now in Final Declaration

  4. Overall, the Park has sold 18 Units representing $9M in revenues, over $8M in greenhouse payments have already been received

  5. Grand Opening of Phase I Part A is currently planned for late Dec 2025

  6. PowerPlant Park has concluded operations of one-year delivery pilot in Marin & Sonoma counties. The pilot exceeded sales projections by 40% and achieved the number one rating for all metrics on Weedmaps with over 350 5-star reviews

  7. The Park has designed a 144 sq ft “Kiosk” that can be placed in existing high-volume Storefronts, showcasing only PowerPlant Park brands sold by highly trained Park staff

  8. The Park has developed a “Retail Garage” storefront model where customers can drive through and pick up their purchase of the freshest product in the State without getting out of the car. Orders sent and paid for through PowerPlant Park’s retail phone app. Customer transactions are completed in 8 seconds. Plans are underway to open 4 locations along Bay Area freeway corridors in support of PowerPlant Park Delivery